Time and Work · Exercise 4 of 5

Time and Work Exam Pattern Mix

  • 65 questions
  • Page 1 of 7
  • Answers explained
0Attempted
0Correct
0Wrong
Directions

65 moderate and difficult time and work questions, including a work-timeline chart and a wage table for data interpretation, in the style of IBPS / SBI PO and Clerk, RRB NTPC and Group D, UPSC CSAT, state PSC and IT campus placement tests.

Question 1 Medium

A can finish a job in 18 days. After working alone for 6 days he gets B's help, and together they finish it in 4 more days. How long would B alone take?

A 12 days
B 6 days
C 9 days
D 18 days
Discuss in Forum
Question 2 Medium

A, B and C together finish a job in 6 days, and A and B together in 8 days. How long would C alone take?

A 24 days
B 2 days
C 14 days
D 48 days
Discuss in Forum
Question 3 Hard

A is 30% more efficient than B, and together they finish a job in 10 days. How long would B alone take?

A 17.7 days
B 20 days
C 23 days
D 13 days
Discuss in Forum
Question 4 Medium

A can finish a job in 20 days and B in 30 days. A works 5 days, B works 15 days, and C finishes the job in 5 days. How long would C alone take?

A 15 days
B 20 days
C 25 days
D 10 days
Discuss in Forum
Question 5 Hard

A team can finish a job in 20 days. After 5 days two members fall ill and the team's speed drops by 20%. How many days in all does the job take?

A 24 days
B 25 days
C 22 1/2 days
D 23 3/4 days
Discuss in Forum
Question 6 Medium

A and B together finish a job in 24 days, and B is half as efficient as A. How long would A alone take?

A 48 days
B 36 days
C 72 days
D 32 days
Discuss in Forum
Question 7 Hard

Ram can finish a project in 20 days and Shyam in 30 days. Ram works only Monday to Friday and Shyam only on Saturday and Sunday. Starting on a Monday, on which day of the project is it finished?

A Day 21
B Day 24
C Day 20
D Day 22
Discuss in Forum
Question 8 Medium

A and B together build one-third of a wall in 4 days, and A alone builds one-fourth of it in 6 days. How long would B alone take?

A 12 days
B 18 days
C 24 days
D 36 days
Discuss in Forum
Question 9 Hard

A and B together finish a job in 15 days, B and C in 20 days, and all three in 12 days. How long would B alone take?

A 30 days
B 60 days
C 20 days
D 24 days
Discuss in Forum
Question 10 Medium

A can finish a job in 9 days, and B takes 50% more time than A. How long will they take together?

A 5.4 days
B 3.6 days
C 4.5 days
D 6 days
Discuss in Forum