A and B together finish a job in 15 days, B and C in 20 days, and all three in 12 days. How long would B alone take?

  • A 30 days Correct
  • B 60 days
  • C 20 days
  • D 24 days
Correct Answer: Option A

A = 1/12 − 1/20 = 1/30

C = 1/12 − 1/15 = 1/60

B = 1/12 − 1/30 − 1/60 = 2/60 = 1/30

B alone = 30 days

Answer: 30 days