Time and Work · Exercise 4 of 6

Time and Work Exam Pattern Mix

  • 65 questions
  • Page 3 of 7
  • Answers explained
0Attempted
0Correct
0Wrong
Directions

65 moderate and difficult time and work questions, including a work-timeline chart and a wage table for data interpretation, in the style of IBPS / SBI PO and Clerk, RRB NTPC and Group D, UPSC CSAT, state PSC and IT campus placement tests.

Question 21 Medium

A makes 20 toys in 8 hours and B makes 30 toys in 10 hours. Working together, how long will they take to make 110 toys?

A 22 hours
B 20 hours
C 18 hours
D 25 hours
Discuss in Forum
Question 22 Hard

A can build a wall in 10 days and B can knock it down in 15 days. They work at the same time for 5 days, then B stops. How long does A take to finish the wall?

A 5 days
B 10 days
C 6 2/3 days
D 8 1/3 days
Discuss in Forum
Question 23 Medium

A can finish a job in 12 days, and A and B together in 7.5 days. How long would B alone take?

A 4.5 days
B 20 days
C 18 days
D 24 days
Discuss in Forum
Question 24 Hard

A can finish a job in 10 days and B in 15 days. A works every day, and B helps him only on every third day. In how many days is the job finished?

A 6 days
B 9 days
C 8 2/5 days
D 8 days
Discuss in Forum
Question 25 Medium

The efficiencies of A and B are in the ratio 4 : 3, and B alone takes 28 days. How long will A alone take?

A 21 days
B 37.3 days
C 24 days
D 16 days
Discuss in Forum
Question 26 Hard

A finishes 25% of a job in 5 days, and then B joins him; together they finish the rest in 6 days. How long would B alone take?

A 12 days
B 15 days
C 13 1/3 days
D 20 days
Discuss in Forum
Question 27 Medium

A and B together finish a job in 18 days, and A alone in 27 days. How long would B alone take?

A 54 days
B 9 days
C 45 days
D 36 days
Discuss in Forum
Question 28 Hard

A does 8% of a job each day and B does 12%. They work together for 3 days, then A leaves. How many more days does B take?

A 2 days
B 3 1/3 days
C 5 days
D 4 days
Discuss in Forum
Question 29 Medium

A, B and C can finish a job in 6, 8 and 12 hours. How long will they take together?

A 2 h 24 min
B 3 h
C 8 h 40 min
D 2 h 40 min
Discuss in Forum
Question 30 Hard

A can finish a job in 15 days and B in 10 days. They start together; A leaves after some days, and B finishes the rest in 5 days. After how many days did A leave?

A 5
B 2
C 3
D 4
Discuss in Forum