A makes 20 toys in 8 hours and B makes 30 toys in 10 hours. Working together, how long will they take to make 110 toys?
A = 2.5 toys an hour; B = 3 toys an hour
Together = 5.5 an hour
Time = 110 ÷ 5.5 = 20 hours
Answer: 20 hours
Time and Work · Exercise 4 of 6
65 moderate and difficult time and work questions, including a work-timeline chart and a wage table for data interpretation, in the style of IBPS / SBI PO and Clerk, RRB NTPC and Group D, UPSC CSAT, state PSC and IT campus placement tests.
A makes 20 toys in 8 hours and B makes 30 toys in 10 hours. Working together, how long will they take to make 110 toys?
A = 2.5 toys an hour; B = 3 toys an hour
Together = 5.5 an hour
Time = 110 ÷ 5.5 = 20 hours
Answer: 20 hours
A can build a wall in 10 days and B can knock it down in 15 days. They work at the same time for 5 days, then B stops. How long does A take to finish the wall?
Net rate = 1/10 − 1/15 = 1/30
5 days = 1/6 built → 5/6 left
A takes 5/6 × 10 = 8⅓ days
Answer: 8⅓ days
A can finish a job in 12 days, and A and B together in 7.5 days. How long would B alone take?
B = 1/7.5 − 1/12 = 2/15 − 1/12 = 1/20
B alone = 20 days
Answer: 20 days
A can finish a job in 10 days and B in 15 days. A works every day, and B helps him only on every third day. In how many days is the job finished?
Job = 30 units; A 3, B 2 a day
Each 3 days: 3 + 3 + 5 = 11 units
6 days = 22; days 7 and 8 = 6 → 28
Day 9 (A + B = 5) needs 2 units = 2/5 day
Total = 8⅖ days
Answer: 8⅖ days
The efficiencies of A and B are in the ratio 4 : 3, and B alone takes 28 days. How long will A alone take?
Times are in the inverse ratio 3 : 4
A = 28 × 3/4 = 21 days
Answer: 21 days
A finishes 25% of a job in 5 days, and then B joins him; together they finish the rest in 6 days. How long would B alone take?
A = 5% a day
Rest 75% in 6 days → 12.5% a day together
B = 7.5% a day → 100/7.5 = 13⅓ days
Answer: 13⅓ days
A and B together finish a job in 18 days, and A alone in 27 days. How long would B alone take?
B = 1/18 − 1/27 = (3 − 2)/54 = 1/54
B alone = 54 days
Answer: 54 days
A does 8% of a job each day and B does 12%. They work together for 3 days, then A leaves. How many more days does B take?
3 days together = 60% → 40% left
B = 12% a day → 40/12 = 3⅓ days
Answer: 3⅓ days
A, B and C can finish a job in 6, 8 and 12 hours. How long will they take together?
Job = 24 units; rates 4, 3, 2 → 9 an hour
Time = 24/9 = 2⅔ h = 2 h 40 min
Answer: 2 h 40 min
A can finish a job in 15 days and B in 10 days. They start together; A leaves after some days, and B finishes the rest in 5 days. After how many days did A leave?
Job = 30 units; A 2, B 3 a day
B's last 5 days = 15 units
First x days together: 5x = 15 → x = 3
Answer: 3