| = | ![]() | 29952 | x 360º | ![]() | = 187.2º |
| 57600 |
Pie Charts · Exercise 8 of 8
Pie Charts Pie Chart 8
- 5 questions
- Page 1 of 1
- Answers explained
Directions
The following pie-chart shows the sources of funds to be collected by the National Highways Authority of India (NHAI) for its Phase II projects. Study the pie-chart and answers the question that follow.
Sources of funds to be arranged by NHAI for Phase II projects (in crores Rs.)

| 20% of the total funds to be arranged |
| = Rs. (20% of 57600) crores | |
= Rs. 11520 crores Rs. 11486 crores. |
Rs. 11486 crores is the amount of funds to be arranged through External Assistance.
Amount permitted =
(Funds required from Toll for projects of phase II)
+ (10% of these founds)
= Rs. 4910 crores + Rs.(10% of 4910) crores.
= Rs. (4910 + 491)
= Rs. 5401 crores.
| Required ratio = | 4910 | = | 1 | ![]() | 1 | . |
| 29952 | 6.1 | 6 |
| Shortage of funds arranged through External Assistance | ![]() |
| = Rs. (11486 - 9695) crores | |||
|
Increase required in Market Borrowing
= Rs. 1791 crores.
| Percentage increase required = | ![]() | 1791 | x 100 | ![]() | % |
| 29952 |
6%.Ready to test your Aptitude?
Timed online tests with instant scores and explanations.