Question 24
Back to Exercise
A can finish a job in 10 days and B in 15 days. A works every day, and B helps him only on every third day. In how many days is the job finished?
- A 6 days
- B 9 days
- C 8 2/5 days Correct
- D 8 days
Correct Answer: Option C
Job = 30 units; A 3, B 2 a day
Each 3 days: 3 + 3 + 5 = 11 units
6 days = 22; days 7 and 8 = 6 → 28
Day 9 (A + B = 5) needs 2 units = 2/5 day
Total = 8⅖ days
Answer: 8⅖ days