A can do ![]() ![]() |
|||||||
Answer: Option C Explanation: ∵ 1/3 of work is done by A in 5 days. ∴ Whole work will be done by A in 15 days. ∵ 2/3 of work is done by B in 10 days. Whole work will be done by B in 10 x (5/2) i.e., 25days ∴ (A + B)'s 1 day's work = (1/15 + 1/25) = 8/75 So, both together can finish it in 75/8 days, i.e., 93/8 days. |