Quantitative Aptitude

General Questions

Quantitative Aptitude Exercise Mode

General Questions

Practice and master this topic with our carefully crafted questions.

4 Questions
6 Minutes
0% Completed
QUEST ? !
Question 41
A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work?

A
18 days
B
24 days
C
30 days
D
36 days
Correct Answer: Option A

2(A + B + C)'s 1 day's work

= ( 1 + 1 + 1 ) = 15 = 1 .
30 24 20 120 8

Therefore, (A + B + C)'s 1 day's work

= 1 = 1 .
2 x 8 16

Work done by A, B, C in 10 days = 10 = 5 .
16 8

Remaining work = ( 1 - 5 ) = 3 .
8 8

A's 1 day's work = ( 1 - 1 ) = 1 .
16 24 48

Now, 1 work is done by A in 1 day.
48

So, 3 work will be done by A in ( 48 x 3 )
8 8

= 18 days.

Question 42
A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?

A
30 days
B
40 days
C
60 days
D
70 days
Correct Answer: Option C

Let A's 1 day's work = x and B's 1 day's work = y.

Then, x + y = 1 and 16x + 44y = 1.
30

Solving these two equations, we get:

x = 1 and y = 1
60 60

B's 1 day's work = 1 .
60

Hence, B alone shall finish the whole work in 60 days.

Question 43
A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in :

A
4 days
B
6 days
C
8 days
D
12 days
Correct Answer: Option C

(A + B + C)'s 1 day's work = 1 ;
6

(A + B)'s 1 day's work = 1 ;
8

(B + C)'s 1 day's work = 1 .
12

Therefore (A + C)'s 1 day's work
= ( 2 x 1 ) - ( 1 + 1 )
6 8 12
= ( 1 - 5 (
3 24
= 3
24
= 1 .
8

So, A and C together will do the work in 8 days.

Question 44
X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?

A
131/3 days
B
15 days
C
20 days
D
26 days
Correct Answer: Option A

Work done by X in 8 days = ( 1 x 8 ) = 1 .
40 5

Remaining work = ( 1 - 1 ) = 4 .
5 5

Now, 4 work is done by Y in 16 days.
5

Whole work will be done by Y in:

( 16 x 5 ) = 20 days.
4

Therefore X's 1 day's work = 1 , Y's 1 day's work = 1 .
40 20

(X + Y)'s 1 day's work = ( 1 + 1 ) = 3 .
40 20 40

Hence, X and Y will together complete the work in:

( 40 ) = 13 1 days.
3 3