Hard Level Question 17 – answer, explanation & discussion

  • 0 comments
  • Answer explained
  • Moderated community
Question 17 Back to Exercise

A can finish a job in 10 days, B in 15 days and C in 30 days. A works alone on day 1, B joins on day 2, C joins on day 3, and all three work from then on. In how many days is the job finished?

  • A 5 days
  • B 6 days
  • C 6 1/3 days
  • D 5 2/3 days Correct
Correct Answer: Option D

Job = 30 units; A 3, B 2, C 1 a day

Day 1: 3; day 2: 5 → 8

From day 3: 6 a day for 22 units = 3⅔ days

Total = 2 + 3⅔ = 5⅔ days

Answer: 5⅔ days