Time and Work · Exercise 3 of 6

Time and Work Hard Level

  • 40 questions
  • Page 2 of 4
  • Answers explained
0Attempted
0Correct
0Wrong
Directions

40 hard time and work questions for bank mains, CSAT and state PSC: workers leaving at different times, changing efficiency, three-way combinations, wages for partial work, the √(a·b) shortcut, rotations and a bar-chart data-interpretation set.

Question 11 Hard

A starts a job. B joins after 4 days and C after 2 more days, and the job is finished on day 10. A alone takes 20 days and B 30 days. How long would C alone take?

A 15 days
B 12 days
C 13 1/3 days
D 20 days
Discuss in Forum
Question 12 Hard

The efficiencies of A, B and C are in the ratio 2 : 3 : 5. A and C together finish a job 4 days sooner than A and B together. How long would A alone take?

A 35 days
B 28 days
C 40 days
D 30 days
Discuss in Forum
Question 13 Hard

A can finish a job in 12 days and B in 18 days. B works every day, while A works only on alternate days, starting on the first day. In how many days is the job finished?

A 9 days
B 10 days
C 10 1/5 days
D 11 days
Discuss in Forum
Question 14 Hard

A is 50% more efficient than B. A works for 8 days and B for 12 days, and the job is done. They are paid ₹ 4,800. What is A's share?

A ₹ 2,880
B ₹ 2,400
C ₹ 1,920
D ₹ 2,000
Discuss in Forum
Question 15 Hard

A and B can finish a job in 10 days, B and C in 12 days, and C and A in 15 days. All three start; A leaves after 2 days and B 3 days after that. How many days in all does the job take?

A 20 days
B 22 days
C 18 days
D 25 days
Discuss in Forum
Question 16 Hard

A takes x days and B takes (x + 6) days to finish a job, and together they take 4 days. How long does B alone take?

A 6 days
B 12 days
C 10 days
D 8 days
Discuss in Forum
Question 17 Hard

A can finish a job in 10 days, B in 15 days and C in 30 days. A works alone on day 1, B joins on day 2, C joins on day 3, and all three work from then on. In how many days is the job finished?

A 5 days
B 6 days
C 6 1/3 days
D 5 2/3 days
Discuss in Forum
Question 18 Hard

The bar chart shows how many days each of five workers takes to finish a job alone.

Days taken alone
A12 daysB15 daysC20 daysD30 daysE60 days

Which two workers together would take exactly 20 days?

A C and E
B C and D
C D and E
D B and E
Discuss in Forum
Question 19 Hard

The bar chart shows how many days each of five workers takes to finish a job alone.

Days taken alone
A12 daysB15 daysC20 daysD30 daysE60 days

How many days will C, D and E take working together?

A 10 days
B 12 days
C 15 days
D 36.7 days
Discuss in Forum
Question 20 Hard

The bar chart shows how many days each of five workers takes to finish a job alone.

Days taken alone
A12 daysB15 daysC20 daysD30 daysE60 days

All five start together. After 2 days A and B leave. How many more days do C, D and E take to finish?

A 6 days
B 8 days
C 4 days
D 5 days
Discuss in Forum