A, B and C together finish a job in 4 days. A alone takes 12 days and B alone 18 days. How long will C alone take?

  • A 6 days
  • B 12 days
  • C 15 days
  • D 9 days Correct
Correct Answer: Option D

Job = 36 units; together 9 a day

A = 3, B = 2 → C = 4 a day

C alone = 36 ÷ 4 = 9 days

Answer: 9 days