Question 30
Back to Exercise
A, B and C together finish a job in 4 days. A alone takes 12 days and B alone 18 days. How long will C alone take?
- A 6 days
- B 12 days
- C 15 days
- D 9 days Correct
Correct Answer: Option D
Job = 36 units; together 9 a day
A = 3, B = 2 → C = 4 a day
C alone = 36 ÷ 4 = 9 days
Answer: 9 days