Question 23
Back to Exercise
A does 5% of a job each day and B does 4%. How long will they take to finish it together?
- A 11 1/9 days Correct
- B 9 days
- C 12.5 days
- D 22.5 days
Correct Answer: Option A
Together = 9% a day
Days = 100 ÷ 9 = 11 1/9
Answer: 11 1/9 days