Question 18
Back to Exercise
In how many days will the job be finished?
I. A (12 days alone) and B (6 days alone) start together.
II. They take Sundays off.
- A Statement I alone is sufficient, but Statement II alone is not sufficient Correct
- B Statement II alone is sufficient, but Statement I alone is not sufficient
- C Each statement alone is sufficient
- D Both statements together are sufficient, but neither statement alone is sufficient
- E Statements I and II together are not sufficient
Correct Answer: Option A
I: 12 × 6/18 = 4 working days. Sufficient.
II: no rates at all. Not sufficient.
Discussion & Comments 0
Share your method, a shortcut, or ask about a step you didn't follow.
No comments yet. Be the first to share your solution!