How long will the job take if A and B work on alternate days?
I. A alone takes 10 days.
II. A works faster than B.
B's time is never given.
Not sufficient even together.
Time and Work · Exercise 5 of 6
20 data sufficiency questions on time and work.
Directions: each question is followed by two statements. Decide whether the data in the statements is sufficient to answer the question, and choose the matching option.
How long will the job take if A and B work on alternate days?
I. A alone takes 10 days.
II. A works faster than B.
B's time is never given.
Not sufficient even together.
How long would A alone take?
I. A is 50% more efficient than B.
II. B alone takes 30 days.
I alone: no actual time. Not sufficient.
II alone: nothing about A. Not sufficient.
Together: 30 ÷ 1.5 = 20 days. Sufficient.
How long will 3 identical machines take to do the job together?
I. One such machine takes 12 hours.
II. The machines are new.
I: 12 ÷ 3 = 4 hours. Sufficient.
II: says nothing about speed. Not sufficient.
What part of the job is left?
I. A and B worked together.
II. A (10 days alone) and B (15 days alone) worked together for 3 days.
I: no rates or time. Not sufficient.
II: 3 × (1/10 + 1/15) = 1/2 done → 1/2 left. Sufficient.
How long would B alone take?
I. A alone takes 12 days, and A and B together take 8 days.
II. B does one-sixth of the job in 4 days.
I: 1/8 − 1/12 = 1/24 → 24 days. Sufficient.
II: 4 × 6 = 24 days. Sufficient.
How long will A and B take together?
I. A alone takes 18 days.
II. B is twice as efficient as A.
I alone: B unknown. Not sufficient.
II alone: no actual time. Not sufficient.
Together: B = 9 days → 18 × 9/27 = 6 days. Sufficient.
How much will C be paid?
I. A, B and C did a job together for ₹ 6,000.
II. C worked fewer days than A.
No rates or amounts of work are given.
Not sufficient even together.
In how many days will the job be finished?
I. A (12 days alone) and B (6 days alone) start together.
II. They take Sundays off.
I: 12 × 6/18 = 4 working days. Sufficient.
II: no rates at all. Not sufficient.
How long would A alone take?
I. A does 25% of the job in 5 days.
II. A does three-fourths of the job in 15 days.
I: 5 × 4 = 20 days. Sufficient.
II: 15 × 4/3 = 20 days. Sufficient.
For how many days did A work?
I. A left before the job was finished.
II. A (20 days alone) and B (30 days alone) started together; A left, B finished alone, and the job took 20 days in all.
I: no figures. Not sufficient.
II: x/20 + 20/30 = 1 → x = 6⅔ days. Sufficient.