A 15 km road is to be built in 300 days, and 75 men are employed. After 100 days only 3 km is built. How many more men must be employed to finish on time?
Rate = 3 km ÷ 7,500 man-days
Left = 12 km = 30,000 man-days in 200 days
Men needed = 150 → more = 75
Answer: 75