Question 12
Back to Exercise
3 men or 5 boys can do a job in 24 days. How long will 6 men and 5 boys take?
- A 8 days Correct
- B 12 days
- C 6 days
- D 9 days
Correct Answer: Option A
5 boys = 3 men
Team = 6 + 3 = 9 men
Job = 72 man-days
Days = 72 ÷ 9 = 8
Answer: 8 days