3 men or 5 boys can do a job in 24 days. How long will 6 men and 5 boys take?

  • A 8 days Correct
  • B 12 days
  • C 6 days
  • D 9 days
Correct Answer: Option A

5 boys = 3 men

Team = 6 + 3 = 9 men

Job = 72 man-days

Days = 72 ÷ 9 = 8

Answer: 8 days