A 15 km road is to be built in 300 days, and 75 men are employed. After 100 days only 3 km is built. How many more men must be employed to finish on time?

  • A 150
  • B 50
  • C 75 Correct
  • D 100
Correct Answer: Option C

Rate = 3 km ÷ 7,500 man-days

Left = 12 km = 30,000 man-days in 200 days

Men needed = 150 → more = 75

Answer: 75