Question 35
Back to Exercise
A can finish a job in 14 days working 6 hours a day, and B in 21 days working 8 hours a day. How many days will they take together working 7 hours a day?
- A 7 days
- B 8 days Correct
- C 10 days
- D 9 days
Correct Answer: Option B
A = 84 hours, B = 168 hours for the job
Per hour together = 1/84 + 1/168 = 3/168
Per day = 7 × 3/168 = 1/8
Days = 8
Answer: 8 days
Discussion & Comments 0
Share your method, a shortcut, or ask about a step you didn't follow.
No comments yet. Be the first to share your solution!