A, B and C can finish a job in 18, 24 and 36 days. A works alone for the first 3 days, and then B and C join him. In how many days in all is the job finished?

  • A 9 2/3 days Correct
  • B 8 days
  • C 10 days
  • D 11 days
Correct Answer: Option A

Job = 72 units; A 4, B 3, C 2 a day

A's 3 days = 12 → 60 left

All three = 9 a day → 6⅔ days

Total = 9⅔ days

Answer: 9⅔ days