Time and Work · Discussion forum

Exam Pattern Mix Question 31 – answer, explanation & discussion

  • 0 comments
  • Answer explained
  • Moderated community
Question 31 Back to Exercise

A can do 25% of a job in 3 days and B can do 20% of it in 4 days. How long will they take together?

  • A 7.5 days Correct
  • B 8 days
  • C 16 days
  • D 6 days
Correct Answer: Option A

A alone = 12 days; B alone = 20 days

Together = 12 × 20/32 = 7.5 days

Answer: 7.5 days