Question 4 Back to Exercise

The flow chart shows a bill being valued today.

Valuing a bill
Sum ₹1,560due in 2 yearsat 15% SIPW ?

What is the present worth of the bill?

  • A ₹ 1,092
  • B ₹ 1,248
  • C ₹ 1,200 Correct
  • D ₹ 1,300
Correct Answer: Option C

rt = 15 × 2 = 30

PW = 100 × 1,560 ÷ 130

= ₹ 1,200

Trap: ₹ 1,092 takes 30% off the sum due.

Answer: ₹ 1,200