Question 40
Back to Exercise
25 men can reap a field in 20 days. After how many days should 5 men leave so that the work is finished in 23 days?
- A 15
- B 10
- C 12
- D 8 Correct
Correct Answer: Option D
Job = 500 man-days
25x + 20(23 − x) = 500
5x + 460 = 500 → x = 8
Answer: 8