Question 36
Back to Exercise
36 men finish half of a job in 20 days. How many more men are needed to finish the other half in 15 days?
- A 48
- B 12 Correct
- C 9
- D 16
Correct Answer: Option B
Half = 36 × 20 = 720 man-days
In 15 days: 720 ÷ 15 = 48 men
More = 48 − 36 = 12
Answer: 12