Question 36 Back to Exercise

36 men finish half of a job in 20 days. How many more men are needed to finish the other half in 15 days?

  • A 48
  • B 12 Correct
  • C 9
  • D 16
Correct Answer: Option B

Half = 36 × 20 = 720 man-days

In 15 days: 720 ÷ 15 = 48 men

More = 48 − 36 = 12

Answer: 12