A contractor has 100 men to finish a job in 40 days. After 30 days only three-fifths of the job is done. How many more men are needed to finish on time?
- A 100 Correct
- B 200
- C 150
- D 50
Correct Answer: Option A
Three-fifths = 3,000 man-days → whole job = 5,000
Left = 2,000 man-days in 10 days → 200 men
More = 200 − 100 = 100
Answer: 100