X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work? |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Answer: Option A Explanation:
Whole work will be done by Y in:
Hence, X and Y will together complete the work in:
|