1. |
A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in : |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Answer: Option C Explanation:
So, A and C together will do the work in 8 days. |