A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work? |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Answer: Option A Explanation: 2(A + B + C)'s 1 day's work
Therefore, (A + B + C)'s 1 day's work
= 18 days. |