1. |
X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last? |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Answer: Option B Explanation:
= 6 days. Hence, total time taken = (6 + 4) days = 10 days. |