1. |
P can do piece of work in 12 days, while Q alone can finish it in 8 days. With the help of R, they can finish the work in 4 days. How long will R take to finish the work alone ? |
|||||||||
Answer: Option D Explanation: P's 1 day's work = 1/12 Q's 1 day's work = 1/8 (P + Q)'s 1 day's work = (1/12) + (1/8) = (2 + 3)/24 = 5/24 (P + Q + R)'s 1 day's work = 1/4 ∴ R's 1 day's work = (1/4) - (5/24) = (6 - 5)/24 = 1/24 ∴ R will finish the work alone in 24 days. ∴ Required time = 24 days |