1. |
Rohan and Sunil separately can complete a work in 8 hours and 4 hours respectively. How much time will they take when working together ? |
|||||||
Answer: Option A Explanation: Required time taken to complete the work by both together = x y / x + y (Here x = 8 and y = 4) ∴ Required time = (8 x 4)/(8 + 4) = 32/12 = 22/3 hours |