Question 30 Back to Exercise

20 men working at 75% efficiency finish a job in 16 days. How long will 15 men working at full efficiency take?

  • A 16 days Correct
  • B 21.3 days
  • C 12 days
  • D 18 days
Correct Answer: Option A

Effective men = 20 × 0.75 = 15

Job = 15 × 16 = 240 full man-days

15 full-efficiency men take 16 days

Answer: 16 days