Question 29
Back to Exercise
12 men working 9 hours a day can finish a job in 20 days. After 10 days, they cut their hours to 6 a day. In how many days in all is the job finished?
- A 30 days
- B 25 days Correct
- C 15 days
- D 22.5 days
Correct Answer: Option B
Man-hours left = 12 × 9 × 10 = 1,080
Per day now = 12 × 6 = 72
1,080 ÷ 72 = 15 more days
Total = 10 + 15 = 25 days
Answer: 25 days