9 masons lay 4,500 bricks in 5 days. How many days will 12 masons take to lay 8,400 bricks?

  • A 7 days Correct
  • B 9 days
  • C 6 days
  • D 8 days
Correct Answer: Option A

Bricks per mason-day = 4,500 ÷ 45 = 100

Days = 8,400 ÷ (12 × 100) = 7

Answer: 7 days