Question 22
Back to Exercise
50 men are to finish a job in 24 days. After 8 days, 10 men leave. By how many days will the job be delayed?
- A 20 days
- B 4 days Correct
- C 6 days
- D 2 days
Correct Answer: Option B
Work left = 50 × 16 = 800 man-days
40 men take 800 ÷ 40 = 20 days (instead of 16)
Delay = 4 days
Answer: 4 days