Question 22 Back to Exercise

50 men are to finish a job in 24 days. After 8 days, 10 men leave. By how many days will the job be delayed?

  • A 20 days
  • B 4 days Correct
  • C 6 days
  • D 2 days
Correct Answer: Option B

Work left = 50 × 16 = 800 man-days

40 men take 800 ÷ 40 = 20 days (instead of 16)

Delay = 4 days

Answer: 4 days