40 men are to build a 200 m wall in 18 days. After 8 days only 64 m is built. How many more men are needed to finish on time?
- A 68
- B 20
- C 32
- D 28 Correct
Correct Answer: Option D
Rate = 64 m ÷ 320 man-days = 0.2 m per man-day
Left = 136 m in 10 days → 136 ÷ (0.2 × 10) = 68 men
More men = 68 − 40 = 28
Answer: 28