15 men finish one-third of a job in 10 days. How many more men are needed to finish the rest in 10 days?
- A 30
- B 10
- C 15 Correct
- D 20
Correct Answer: Option C
One-third = 150 man-days → rest (two-thirds) = 300 man-days
In 10 days: 30 men
More men = 30 − 15 = 15
Trap: 30 is the total, not the extra.
Answer: 15