15 men finish one-third of a job in 10 days. How many more men are needed to finish the rest in 10 days?

  • A 30
  • B 10
  • C 15 Correct
  • D 20
Correct Answer: Option C

One-third = 150 man-days → rest (two-thirds) = 300 man-days

In 10 days: 30 men

More men = 30 − 15 = 15

Trap: 30 is the total, not the extra.

Answer: 15