25 men working 8 hours a day dig 300 m of a canal in 12 days. In how many days will 40 men working 6 hours a day dig 450 m?

  • A 15 days Correct
  • B 12 days
  • C 18 days
  • D 13.5 days
Correct Answer: Option A

Days = 12 × (25 × 8)/(40 × 6) × (450/300)

= 12 × 5/6 × 3/2

= 15 days

Answer: 15 days