Question 2
Back to Exercise
25 men working 8 hours a day dig 300 m of a canal in 12 days. In how many days will 40 men working 6 hours a day dig 450 m?
- A 15 days Correct
- B 12 days
- C 18 days
- D 13.5 days
Correct Answer: Option A
Days = 12 × (25 × 8)/(40 × 6) × (450/300)
= 12 × 5/6 × 3/2
= 15 days
Answer: 15 days