20 men start a job planned for 30 days. After 12 days, 10 more men join. In how many days in all is the job finished?

  • A 20 days
  • B 12 days
  • C 24 days Correct
  • D 26 days
Correct Answer: Option C

Job = 20 × 30 = 600 man-days

Done in 12 days = 240 → left 360

30 men finish 360 in 12 days

Total = 12 + 12 = 24 days

Trap: 12 days is only the second part.

Answer: 24 days