20 men start a job planned for 30 days. After 12 days, 10 more men join. In how many days in all is the job finished?
- A 20 days
- B 12 days
- C 24 days Correct
- D 26 days
Correct Answer: Option C
Job = 20 × 30 = 600 man-days
Done in 12 days = 240 → left 360
30 men finish 360 in 12 days
Total = 12 + 12 = 24 days
Trap: 12 days is only the second part.
Answer: 24 days