Question 37
Back to Exercise
18 men do two-thirds of a job in 12 days. How many days will 12 men take to finish the rest?
- A 18 days
- B 9 days Correct
- C 6 days
- D 12 days
Correct Answer: Option B
Two-thirds = 216 man-days → whole job = 324
Rest = 108 man-days
12 men take 9 days
Answer: 9 days