Question 33
Back to Exercise
20 men working 8 hours a day dig 40 m of a tunnel in 10 days. The next 60 m is through rock that is 25% harder. How many men working 10 hours a day will dig it in 12 days?
- A 25 Correct
- B 20
- C 30
- D 24
Correct Answer: Option A
Man-hours per metre = 1,600 ÷ 40 = 40 → 50 in rock
60 m needs 3,000 man-hours
Each man works 10 × 12 = 120 hours
Men = 3,000 ÷ 120 = 25
Answer: 25
Discussion & Comments 0
Share your method, a shortcut, or ask about a step you didn't follow.
No comments yet. Be the first to share your solution!