A contractor hires 150 men to finish a job in 100 days. After 40 days half the job is done. How many men can he let go and still finish exactly on time?

  • A 50 Correct
  • B 100
  • C 60
  • D 75
Correct Answer: Option A

Half = 150 × 40 = 6,000 man-days

Other half = 6,000 in 60 days → 100 men

Let go = 150 − 100 = 50

Answer: 50