Question 3
Back to Exercise
A contractor hires 150 men to finish a job in 100 days. After 40 days half the job is done. How many men can he let go and still finish exactly on time?
- A 50 Correct
- B 100
- C 60
- D 75
Correct Answer: Option A
Half = 150 × 40 = 6,000 man-days
Other half = 6,000 in 60 days → 100 men
Let go = 150 − 100 = 50
Answer: 50