Question 34
Back to Exercise
25 tailors stitch 300 shirts in 8 days. How many days will 30 tailors take to stitch 360 shirts?
- A 9.6 days
- B 6.7 days
- C 8 days Correct
- D 10 days
Correct Answer: Option C
Days = 8 × (25/30) × (360/300)
= 8 × 5/6 × 6/5 = 8
Answer: 8 days