Question 31 Back to Exercise

60 men can finish a job in 40 days. How many more men are needed to finish it 10 days earlier?

  • A 80
  • B 20 Correct
  • C 15
  • D 10
Correct Answer: Option B

Man-days = 60 × 40 = 2,400

In 30 days: 2,400 ÷ 30 = 80 men

More men = 80 − 60 = 20

Trap: 80 is the total, not the extra.

Answer: 20