Question 31
Back to Exercise
60 men can finish a job in 40 days. How many more men are needed to finish it 10 days earlier?
- A 80
- B 20 Correct
- C 15
- D 10
Correct Answer: Option B
Man-days = 60 × 40 = 2,400
In 30 days: 2,400 ÷ 30 = 80 men
More men = 80 − 60 = 20
Trap: 80 is the total, not the extra.
Answer: 20