The work of 2 men equals the work of 3 boys. 4 men and 3 boys finish a job in 10 days. How long will 6 men and 9 boys take?

  • A 6 days
  • B 4 days
  • C 5 days Correct
  • D 7.5 days
Correct Answer: Option C

3 boys = 2 men

4 men + 3 boys = 6 men → job = 60 man-days

6 men + 9 boys = 6 + 6 = 12 men

Days = 60 ÷ 12 = 5

Answer: 5 days