Question 12
Back to Exercise
25 workers dig a 50 m trench in 10 days. How many days will 30 workers take to dig a 72 m trench?
- A 14.4 days
- B 12 days Correct
- C 10 days
- D 8.3 days
Correct Answer: Option B
Days = 10 × (25/30) × (72/50)
= 10 × 5/6 × 1.44
= 12 days
Answer: 12 days