6 men working 8 hours a day finish a job in 10 days. How many days will 8 men working 6 hours a day take?

  • A 13 1/3 days
  • B 7.5 days
  • C 10 days Correct
  • D 12 days
Correct Answer: Option C

Man-hours = 6 × 8 × 10 = 480

Per day now = 8 × 6 = 48

Days = 480 ÷ 48 = 10

Answer: 10 days