15 men can finish a job in 12 days. How many days will 20 men take to finish the same job?

  • A 16 days
  • B 10 days
  • C 8 days
  • D 9 days Correct
Correct Answer: Option D

More men → fewer days (inverse)

Total work = 15 × 12 = 180 man-days

Days = 180 ÷ 20 = 9

Trap: 16 days treats it as direct proportion.

Answer: 9 days